.
News Alert
Flu Makes Easter Resurgence In New Jersey: Has It …

Toms River, Lavallette Beach Replenishment Project Won't Start By Summer 2014

Replenishment was supposed to begin by June, but schedule now looks pushed back until after Labor Day

Beach replenishment work takes place in the Brant Beach section of Long Beach Township, June 2013. (Photo: U.S. Army Corps of Engineers)
Beach replenishment work takes place in the Brant Beach section of Long Beach Township, June 2013. (Photo: U.S. Army Corps of Engineers)
By Douglas Bergen

A federal project to rebuild beaches and dunes between Manasquan Inlet and Barnegat Inlet will not start until after summer, according to the Army Corps of Engineers.

Gov. Chris Christie announced in October an "accelerated schedule" of projects to restore beaches damaged by Superstorm Sandy. The schedule called for the beaches in Toms River and other municipalities on Ocean County's northern barrier island to start in June.

But the work is not likely to start until sometime after Labor Day, according to Ed Voigt and Richard Pearsall of the Army Corps of Engineers Philadelphia District.

A complex array of partnership agreements, environmental permits and other prerequisite planning will keep the project from starting in the spring, they said.

Pearsall said the solicitation for bids will go out in July with awards made in September and construction starting after that.

The schedule affects property owners, beachgoers, vacationers and rental agencies in beach communities hit hard by Superstorm Sandy hit in October 2012. Sandy's storm surge cut through the barrier islands at some points, flattened dunes in other places and eroded beaches. There have also been fears that a nor'easter or hurricane could wreak havoc on communities that are now only protected by temporary berms built after Sandy.

But a summer work schedule would have disrupted the height of the beach season.

State Department of Environmental Protection spokesman Larry Hajna confirmed that the environmental work and design reviews necessary for large-scale beach projects likely led to the delayed schedule.

"You would have expect that there would be some revision to schedules," Hajna said.

The federal government will pick up the full $86 million cost of the initial project. The project area would then be part of a three-year maintenance cycle with the Army Corps of Engineers returning to restore the beaches to the initial project dimensions. 

The federal government pays for 65 percent of the program, while the state Department of Environmental Protection picks up the other 35 percent. Of the state's portion, municipalities are required to contribute 25 percent. That leaves towns responsible for only 8.75 percent of the total cost for subsequent projects.

Two other projects, Long Beach Island and Margate-Longport, look to be on a similar schedule. A project from Ocean City to Sea Isle City may be slightly ahead in the process, with working possibly starting after Labor Day.

This week, Toms River Township Council President Maria Maruca said 13 properties whose owners have not signed easements to allow small slivers of land to be used in the dune projects would have those parcels taken by eminent domain by mid-March.

Lavallette's oceanfront is publicly owned and does not require private easements to be granted for the work to get underway.
Martin January 10, 2014 at 08:36 AM
In Oct., before Election Day, Christie said the dune-building schedule would be "accelerated." Maybe that placated voters for a while. Now the truth comes out. -------- The temporary dunes had better be adequate to withstand the nor'easters and hurricanes coming in the next 10 months, or we're all sunk... again. Toms River politicians had better start pushing up more sand.
suz January 10, 2014 at 08:39 AM
Not totally sure, but I can't help but wonder if the holdouts on the dunes are a big part of the delay.
Deep Throat January 10, 2014 at 09:09 AM
I feel confident that our newly appointed leader Maria Maruca will come to our aid and fight to have the dune timetable pushed up. I also feel confident that our taxes will be abolished in the state of New Jersey.
Ortley Beach Bum January 10, 2014 at 10:28 AM
Maruca has to be better than the guy we had before.
bayway mike January 10, 2014 at 01:11 PM
Surprised????
Mac January 10, 2014 at 01:44 PM
So what this article is saying is that the drying-out Bics uncovered by Hurricane Sandy won’t be covered back up with bigger sandcastles until after the next firemen’s convention in Wildwood? Here comes that photo-op helicopter again to save the day for everyone with a big hug for the needy and bucks for the connected greedy.
Mac January 10, 2014 at 04:35 PM
now that's funny - 'King George's Regime' - talk about having nothing to write home about
rita January 11, 2014 at 09:42 AM
I live in NY. Twenty years ago we had a representativeof the Army Corps of Engineers at our association meeting. The problem was constant flooding of a brook, which was destroying many homes. We were promised a speedy remedy, and 20 later ..no work..constant floods.
Mac January 11, 2014 at 10:43 AM
huh, I didn't know Gilmore had a brother that worked for the Army Corps of Engineers - thanks for sharing rita

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »